Professional Scrum Product Owner I (PSPO I) 2025 – 400 Free Practice Questions to Pass the Exam

Question: 1 / 400

What are the three questions answered by all Development Team members during the Daily Scrum?

What work did I do yesterday?

The correct choice encompasses one of the core components of the Daily Scrum, which is a time-boxed meeting for the Development Team held to synchronize activities and create a plan for the next 24 hours.

In this meeting, each team member shares what they accomplished the day before, which aligns with transparency and accountability within the team. It provides insight into the progress made on the sprint goal, helping the team to understand how much work has been completed and what still needs to achieve the objectives.

While the other choices present valuable questions relevant to team dynamics and personal development, they do not align with the primary purpose of the Daily Scrum. The focus of this meeting is primarily on ongoing work and immediate collaboration rather than personal skills development or specific impediments, which may be discussed in various contexts but are not the standard questions addressed during this particular meeting.

Ultimately, the emphasis on what each individual has accomplished the previous day helps promote a collective awareness of the sprint's status and supports the team in making the necessary adjustments to their tasks for the upcoming day.

Get further explanation with Examzify DeepDiveBeta

What skills do I need to develop?

What work am I doing today?

What impediments are in my path?